Guidance on a Planned Partial Power Outage on CampusAuthor : 관리자Date : 2020.03.10Hit : 852
-
Regarding the construction of the 2nd International Hall, we plan to proceed with the planned partial power outage of buildings near the construction site as follows.
A. Date of Outage: 20:00 - 22:00 (Total 2 hours) on March 11th, 2020
B: Affected Buildings: Nicholls Hall, Maria Hall, Virtus Hall, Bambino Hall, and Chapel of the Sacred Heart
C. Reasons for Outage: Construction power separation work for the construction of the 2nd International Hall
D. Inquiries: Contact the Facilities Management Team (T.4137)
* We apologize for any inconvenience caused by the construction.
-
Attachment File